(1) What is your essential question, and what are your answers?  What is your best answer and why?
My essential question is: What is the most important factor in ensuring profit in a grading operation?
Through my work at my mentorship as well as personal  research I came up with three answers.
1.Proper Estimation.
2.Proper Pre-construction Planning.
3. Proper management on all levels.
All of these fully answer my EQ and are each highly supported by in the field experiences. However my many discussions with my mentor and my second independent component all pointed toward one answer being the best. My first answer( proper estimation) is the best answer to my essential question for four reasons. First, It is the answer that best encompasses and affects construction profit, the main focus of my question. Second, estimation has the most direct relationship to profit (estimation sets up crucial contract prices).  Third, Estimation has the most impact on the construction process as a whole due to compounding factors. Finally it was the most heavily supported,coming up time and time again as the root cause of errors in the grading process.


2. What process did you go through to arrive at your best answer?


The process of finding by best answer was the focus of my second independent component. I looked through various old jobs that my mentorship completed and searched for a pattern or theme with the ones in which profit was not optimal. The most common factor turned out to be errors in estimation. Estimators had improperly predicted the construction cost by not calculating for  soil contamination, the possibility of high material price or simply failed to understand the complete scope of the project. I then had many discussions with my mentor about common factors and he agreed with me. estimation is so often a cause for error because an extremely minor error will compound throughout the project in a butterfly effect. My best answer was also eluded to through my research as improper estimation came up all the time.

(3) What problems did you face?  How did you resolve them?
The first problem i encountered was a lack of sources. There are not many sources on grading and construction, most of the knowledge is learned on the job and the sources i did have from my mentorship were confidential. I was able to overcome this by searching harder for sources and relying more on discussions with my mentor. My second problem was defining proper estimation. Estimation can encompass a lot. talking with my mentor kept helped me define it and differentiate it from construction planning. (the focus of estimation is to calculate the completion price of a project for use in bidding.)

4) What are the two most significant sources you used to answer your essential question and why?
My mentor was my most significant source in finding the answer to my eq, he is extremely well qualified and knowledgeable in the field of grading and estimation. Through sitting in on his meetings and my interviews I learned so much about the problems graders commonly face and how profit is generated throughout the project. My second most significant source was the Earth Tek company records of current and past projects. In these huge files i was able to look through old projects and find out what went wrong. I was able to see the effects of estimation compound through a project and i was able to see how commonly estimation came up as an error. These real life examples were an excellent primary source that showed my essential question in real life.










Tuesday, April 28, 2015

extra april post

Senior project is almost done!!!!
This month the majority of my time was spent on my independent component. Getting hours and recording meetings/ other proofs. I was also able to finalize my activity with la Russa. I am not changing it much from the first one i am just making sure to include elements related to my EQ.Things are really wrapping up, i am almost done with all my sources as well. Im almost done with the paper and my best answer is very well suported. The highlight of my essential question was walking around and going over my mentors project in our parking lot. Earth tek is doing the grading and it is amazing to see them solve problems in real time. There is really not much else to say. I am happy to be done with the required hours but i will most likely keep getting hours for above and beyond. Here is a summary of my mentors qualifications. All is going well and i hope i get a good grade


Tom Chavez

Tom Chavez is Vice president and oversees the estimating and project management team at Earth Tek. Together with staff, they prepare hard competitive bids and also provide value engineering for negotiated projects becoming more prevalent on large projects today. Upon successful award or negotiation, the team coordinates oversight until closeout and completion.
Mr. Chavez began in the construction industry in the early 1980's. Working with several local real-estate developers, the importance of recognizing regional trends and adjusting to changing conditions became apparent. Participation in the successful development of residential and commercial developments has brought a unique perspective to Earth Tek in providing site development and earthwork services to Southern California builders and developers.

Sunday, April 26, 2015

Independent Component Blog

 (a) Include this statement: “I, Joseph Mirabal, affirm that I completed my independent component which represents 30 hours of work.”
(b) My primary source for sure was my mentor tom Chavez  he was extremely helpful in helping me answer my eq, understand estimation and profit in construction and providing activities to help me learn while attaining hours. He also introduced me to other workers and contractors to help me expand my knowledge. My other source is stated below it was great at helping identify things that were going wrong in many of the reports.
Rawlinson, Simon. "Successful Projects." UK Building (2009): n. pag. Web. http://www.aecom.com/deployedfiles/Internet/Capabilities/Program,%20Cost,%20Consultancy/Cost/Procurement_SuccessfulProjects_10Feb06.pdf




(d)For my independent component I learned about the various factors in construction and how they affect profit, in order to best answer my eq. I looked through old construction reports and summaries looking for what went wrong when profit was lost and what went right when profit was generated. I hoped to find a pattern in which a single factor affected profit time and time again through various projects. I attained my thirty hours through reading report after report, talking to my mentor and having my mentor giving me hypothetical situations  so that i could try determine what will go wrong. After narrowing down my answer i then had to discuss differences between estimation and pre construction planning in order to better answer my eq. My independent component was imperative in answering my eq.
INTERPRETIVE DEFEND THE WORK!
How did the component help you answer your EQ? Please include specific examples to illustrate how it helped. 
My EQ is  What is the most important factor in ensuring a profit in a grading operation? I focused my research primarily on my first and second answers. During the project i realized that these answers overlap a lot and i had to differentiate between the two (estimation and pre-construction planning). My independent component had me looking through case after case for factors that affected construction proffit. Time and time again i found that initial errors that should have been accounted for in estimation compounded and deeply affected profit. Cases like the Costco project where they failed to account for large amounts of asbestos when estimating time and profit and are now facing serious consequences. Or the Case where they simply read the contract wrong and graded one foot too deep. These simple errors should have been prevented by properly estimation the scope of the job at the beginning (the estimation stage). Not only were these errors bad but through my cited source reading and the scenarios I went over I saw how these errors compounded through the project. These repeated occurrences deepened my knowledge and proved my first answer as the best answer. It came up the most out of the three and was by far the most impactful due to the compounding effect.  I Am very proud of how well i have gotten at understanding the world of grading and being able to sit in and understand many complicated meetings. By the end both my mentor and i agreed with my first answer and i am very confident in it thanks to my independent component.


I primarily focused in on determining which essential question answer had the most support in the real world. I also had to clarify the difference between my first and second essential questions. In order to find out which factor occurred most often and had the most profound effect on the grading process i had to look through old construction spending reports  I had to look for what went wrong in failed construction jobs and try to find a pattern or common theme. The only way to do this was to parse through report after report each one taking over an hour to fully comprehend and read. I also sat through many construction meetings as well. In these meetings problems they were experiencing were often the topic. Through viewing factors that affect profit in grading first hand i was able to answer my eq and support my findings.

Most of the work i did in finance was confidential and difficult to get evidence for. Here is what i could get

                                                      4
This is some audio of some of the meetings I sat in as well as some of the discussion I had with my mentor.

3/20/2015 completed jobs folders. These folders contain tons of information on past jobs by earth tek, especially on where they went right or wrong.

looking through contracts and estimation plans to find common factors in grading. This work at tustin legacy was quite successful and i noted how well written the initial contract was as well as communication between the owner and earthtek.

here I observed the construction process unfold and how it is well documented.

Here i was able to sneak a picture of some of the finance reports. in this particular project they were very behind schedule due to an error in acquiring supplies. the time delay is noted and cost the company profit.

Here i looked at the building of a school. in the construction there was a wage argument with the construction workers that caused delays. they wanted higher wages and almost started a strike. my mentor stated that they should have finalized the wages in the initial estimation.

http://www.groton-ct.gov/meetings/Handouts/08-22-13%20Building%20Construction%20Scenarios%20%28REVISED%20for%2009-26-13%29.pdf

Link to the scenarios my mentor tested me with. He gave me building criteria and information and i had to explain how certain factors would affect the construction job at hand as well as how to correct them. We also discussed how an estimator must factor in the season as well as the proximity to sewage and water lines. This was actually quite fun.

Very important report on parking lot contract. Earth tek failed to properly grade a surface. they dug  one foot to deep and lost a lot of money.  I discussed with my mentor how they could have avoided this. It was a greed that if they had properly read the contract an essential part of estimation this could have been avoided.
observing work at ipoly noting the placement of gravel and the savings caused by a light rain. this saved money on water needed for dust prevention. Discuessed the scope of the project 80,000 cubic yards of dirt must be removed and the problem of where to put the dirt.



Looking over more cases this was their current work with a costco and the problems they are facing with asbestos contamination. They did not expect so much asbestos and failed to account for it in the initial estimation. because of this they are behind schedule and over budget.

Sitting in on meetings.


observing budget effects of unaccounted for asbestos in construction project.



"Estimation deals with determining a proper price, in order to do this the entire job must be planned out to the finest detail in order to calculate the most accurate price. Estimation should cover all of the planning; they can be interchangeable in a broad sense. My mentor stated, “A proper estimation needs to include the site plan, you cannot estimate without planning the construction out, it is simply impossible”. Planning includes the scheduling of a project another essential aspect in the construction industry. The deep relationship between planning and estimating strengthened my first finding greatly."

excerpt from my findings paper that discusses estimation vs pre-construction planning.
Pre-construction planning deals with the actual building plan and estimation deals with the cost of making the plan a reality. You can not complete a plan without an estimation. Estimation  affects profit and the construction process more and therefore is the better answer and what i focused my component primarily on.


  APPLIED


 

















Monday, March 30, 2015

Extra March Post

March has been quite the month. I have finished my first independent Component and have started my second one. Unfortunately i have run into some hangups. My initial idea of of going through accounts was becoming impossible due to concerns with privacy and my inability to show proof. I was able to get 6 hours however and I did learn a lot about the various factors that impact my EQ. I am now shifting my IC to something that has to do with external factors and their effect on profit. I am still developing the idea with my mentor as well as getting hours, I will discuss this with him more on friday.  I have also discussed my problem with rivas. Last friday we worked on contaminated soils and the problems that they can cause, my IC will be along these lines.

Fun Fact: to treat contaminated ground water molasses is often pumped into aquifers in order to feed microorganisms, who will then eat the contaminants.


My mentor tom, great guy.

So things are startingggg to get back on track which is great. I just need to work more on my WB and work on my activity. The main achievement was the completion of my first component and i plan to finish my second one before the deadline as well as secure my second interview.

Tuesday, March 10, 2015

Blog 14: Independent Component 1

 “I, Joseph Mirabal, affirm that I completed my independent component which represents 31 hours of work.”

Source: This was a small book my mentor gave me on understanding soil reports. Most of my information for my independent component came from primary sources at the offices as well as discussions with my mentor.


Hardy, David H. Understanding the Soil Test Report. Raleigh, NC: NCDA&CS Agronomic Division, 2007. Print. 
What i have completed: For my independent component I conducted in depth research on my project topic of Grading. In order to  better understand the factors that go into Grading and how these influence the process I decided to go step by step through the ENTIRE construction process, from initial bidding to end product. This helped me identify important factors in the grading process, something crucial to answering my essential question  of (what is the most important factor in ensuring a profit in a grading operation). As i identified these important factors I was able to see how they affected the grading process either positively or negatively.
I also got an amazing understanding of the grading process by following every step taken by my mentorship in the construction field specifically on a parking structure in brea. Throughout this process of heavy reading I was often talking to my mentor, asking questions and learning things like how to read blue prints. We often discussed how small things can affect the entire process and ways a company can preserve profit. I also often talked to other co workers who specialized in the area i was currently studying.





This in depth review greatly increased my knowledge on the field of grading and has helped me answer my EQ.


*INTERPRETIVE 
The only way I can successfully answer my EQ is to know all the aspects and factors that go into the grading process. I needed a way to look at each part in an in depth way and following the grading process through an old construction project my mentorship completed was the perfect way to get 30 hours. For me to really understand the process I had to read  and highlight  soooo many papers, reports and contracts that make up the grading process. This coupled with various discussion with my mentor and other employes got me to my 30 hours.
The photos below represent a minute fraction of all the stuff i went through and discussed.

This is the bid folder that contains all the project information.


Day 1 Architectural plans
Below: image of the cut and fill measures of the job. Red indicates cut Blue indicates fill
Architecture plans I went through

Various symbols I have had to memorize in order to understand the plans.
Day 2 1/23/2015
boring report/ calculation dirt removal cost



day 3 1/25/2015
more soil reports


day 4 1/30/2015
Understanding Curb Detail and plumbing plans


day 5 2/6/2015
Erosion Prevention plans/ calculating gradation limits.

day 6 2/13/2015
Understanding bidding/ initial contract


day 7 2/20/2015
Billing/ Payment processing 


day 8: 3/6/2015
Subcontracting and finalization /miscellaneous







  •  Applied  
This independent component helped me understand my component immensely because I followed grading from point A to Z i went into depth on every single aspect as well as discussed these aspects with my mentor throughout. I was able to learn about each factor, something critical to answering my eq. I was also able to look at grading as an entire multi step process, this helped me understand how certain factors can add up and affect the entire process.My mentor taught me many things,  he taught me all the symbols that go into blueprints as well as the aspects that affect bidding. We also discussed the importance of profit. My independent component greatly increased my knowledge of contract grading as well as has helped me answer my eq.

















Monday, March 9, 2015

Blog 18: Fourth Interview Preparation

What is the most important factor in ensuring a profit in a grading operation?
*i will interview my mentor whom i have only interviewed once.

1. What do you believe is is the most important factor in ensuring a profit in a grading operation? and why do you believe this?
2. do you have  any thoughts on my first EQ and how how well do you believe it answers the question.
3. Do you have  any thoughts on my second EQ and how how well do you believe it answers the question.
4. Do you have  any thoughts on my third EQ and how how well do you believe it answers the question.
5. Can you think of any other factor in the grading process that i am missing and may need to research on.
6. How has earthtek tried to optimize profit? and has it worked?
7. What is one way grading estimators can increase their proficiency?
8. What is a common mistake among many estimators and how do mistakes in estimation affect the rest of the construction process?
9. How is planning part of earth treks construction program?
10. DO you believe effective planning benefits the construction process?
11. How does planning compare to estimation in terms of importance?
12. How does proper management factor in to the grading process?
13. What is the management structure of earthtek?
14. what is the most important thing that you have learned as a contract grader?
15. Do you think the answer to my EQ will change depending on who in the office I ask?
16. What factor of construction do you think influences profit the most?
17. WHat are some other ways a construction company can protect profit?
18. Does profit only benefit the owners of the company?
19. What are some commonly overlooked factors in construction?
20. How do you feel about my answer to the EQ?


Thursday, March 5, 2015

Blog 17: Answer 3

1. What is the most important factor in ensuring a profit in a grading operation?

2. Proper Management  on all levels improves efficiency and protects profit.

3.

  • Improper management results in higher incident rates. Incidents can put construction projects behind schedule immensely.  
  • Improper management slows down productivity in the office which results in less bids.
  • Leadership is necessary to prevent time consuming quarrels.
Deshpande, Pushkar V. CONSTRUCTION MANAGEMENT: Preliminary Cost Estimate and Scheduling of MIT's Civil and Environmental Engineering Building. Diss. MASSACHUSETTS INSTITUTE OF TECHNOLOGY, 1999.

In construction time is money. Proper management keeps things running smoothly preventing expensive hold ups.